Concrete Footings
Concrete Footings are the basic item that you need to create a Foundation.
Above are some Pictures of a Footing Before the Concrete is Poured.
Some Building Materials Needed To Construct A Footing.
2"x12" Planks | As Needed |
2"x4" Spreader | Every 4 Feet |
#16 & #8 Nails | As Required |
Perferated Banding | Various Lengths |
Reinforcement Steel | If Necessary |
Steps:
- Layout with Pins & String. Place Long 2x12 Planks along side the String. Also Reinforcement Steel & Keyway if Required.
- Nail all the Corners together. Nail the Spreaders to the Planks. Allign all the Corners and Planks to the Layout String.
- Nail the rest of the Planks & Spreaders together. If Necessary Nail the Keyway in Place and Tie All the Reinforcement Steel.
- Calculate the Concrete Needed. Call the Concrete Truck. Place The Concrete. If Winter Apply Winter Protection.
- Above You Will Find some Pictures of a Footing After the Concrete is Poured and Stripped. Enjoy!